| 
         | 
 
       | 
		||
        
![]() General Approach to Bank Stabilization 
4.2.3 ECONOMIC CONSTRAINTS 
It was pointed out in Section 4.1 that problems generated by bank instability may 
sometimes be most effectively and economically solved by less obvious alternatives than 
site-specific bank stabilization works, especially if the problems are a result of system 
instability. Section 5.3 further discusses economic factors involved in the selection of site- 
specific bank protection methods. However, it may be appropriate at an early stage in project 
planning to consider economic constraints beyond the fundamental engineering concept of 
obtaining the best value for funds expended. Two such factors are: 
Does the viability of the project depend upon a formally calculated favorable 
benefit to cost ratio, or will the project be constructed to satisfy specific needs 
regardless of economic calculations, such as to protect a historic site of 
indeterminate value? The latter provides the most engineering flexibility, but 
the former is the most likely situation, in which case the procedure for 
estimating costs and benefits is probably specified either by the engineer's 
organization or the project sponsor. 
Does the project sponsor have the means and commitment to pay for a 
well-engineered project, including data collection and an analysis of the causes 
of the problems and alternative solutions? If not, it is the engineer's duty to 
point out the hazards of not doing so, in the hope that a more thorough 
analysis will be authorized. 
These considerations are often complicated by the fact that the cost of bank 
stabilization may exceed the economic value of land and facilities to be directly protected. 
However, the economic analysis for projects based on broad studies can include identification 
of less immediately obvious benefits, such as the reduction of sedimentation problems 
downstream, which may have the potential for benefitting flood control, navigation, and 
environmental quality. 
4.2.4 COORDINATION WITH OTHER INTERESTED PARTIES 
Most project requirements will be satisfied by adhering to the suggestions in the 
preceding sections and those in subsequent chapters on design, construction, and 
maintenance. However, there are usually other interested parties who should be notified or 
consulted, at least informally. Viewing the specific situation from an "outsider's" perspective, 
or asking someone less involved in the details of the planning to do so, will usually identify 
those parties, thus identifying potential non-engineering problems early on. Public notices 
that may be required by law can also be used as opportunities in this regard, rather than 
grudgingly satisfying only the letter of the requirement for the notice. 
3 
83 
 | 
			||
![]()  | 
		||