| 
         | 
 
       | 
		||
        
![]() Indirect Techniques for Erosion Protection 
Hardware and fasteners, such as nails, bolts and cable, will be largely dictated by 
the choice of other materials. Corrosion resistant hardware must be used unless the 
work is temporary. 
(b) Structural design is an iterative process. The goal is to achieve the required height and 
permeability in the most economical way, considering the cost of materials and the 
construction techniques that will be used. The variables for fence-type permeable dikes 
are: 
Lateral loads (drag force of current, impact of debris); 
Spacing, size, and penetration of piles; 
Size of sub-components (boards, fencing, cables, anchors); and 
Supplementary bracing. 
The vulnerability to failure from lateral loads increases with dike height, since the 
moment arm of the force is greater, and the amount of debris carried by the stream, as 
well as the speed of impact, is likely to increase as river stage increases. As the height 
of the dike increases, this combination dictates an increase in the size of the structural 
members, as well as an increase in pile penetration for those designs using driven piles. 
These factors cause the cost to increase dramatically as the dike height increases. 
Typical practice for penetration of piles or posts is that at least 1/2 to 2/3 of the 
total length should be in the ground. Factors that influence required penetration are the 
nature of the bed and sub-bed material, the potential for scour, and anticipated lateral 
loads from hydraulic loading and floating debris or ice. The nature of the material 
through which the piles or posts are to be driven must be known in order to determine 
if driving will be feasible. Encountering unanticipated difficulties during the driving 
operation may cause contractual difficulties as well as perhaps necessitating redesign of 
the work. 
If previous experience has developed a design that has been successful in 
applications similar to the project at hand, it is more prudent to apply that experience 
rather than over-extending the safe bounds of theory with numerical structural analysis 
using imprecise assumptions. Figure 8.1 shows some typical designs of permeable dikes. 
(c) Some miscellaneous design considerations are as follows: 
The facing material should be attached to the upstream side of dikes. 
Large trees which may be undermined and fall onto the dikes should be 
removed. Otherwise, existing vegetation should be preserved to the 
greatest extent possible. If clearing of the bank is necessary to provide 
construction access, stumps should be left in the ground, since regrowth of 
some species will occur. 
Cuts made in treated wood members should be recoated with a preservative. 
204 
2 4 
 | 
			||
![]()  | 
		||