| 
         | 
 
       | 
		||
        
![]() Construction of Stabilization Works 
(f) Alternatives available to the construction forces if specifications call for a dike crown 
width too narrow for the operation of construction equipment are to: 
Construct "turn-arounds," or maneuvering areas, by widening the crown at 
intervals along the dike. The expense of doing this will of course be 
reflected, at least indirectly, in the bid price for the work if the work is 
contracted out. 
Construct the top portion of the dike (that portion which is higher than the 
elevation at which there is a crown width sufficient for hauling and handling 
stone) as a separate operation, in which stone that was previously 
"stockpiled" alongside the dike, but outside the specified dike cross-section, 
is pulled up and into the design cross-section. The piece of equipment which 
performs this operation literally backs toward the end of the dike, finishing 
the dike as it proceeds. Some inefficiency is involved in this method, and 
some stone is inevitably left outside the design cross-section, especially if 
some of the stockpiled stone is underwater. 
(g) Stone dikes can be successfully constructed even if the entire structure riverward of the 
bankline is underwater during construction, although careful control of the operation is 
necessary. Precise control of the profile and crown width of the finished structure is not 
feasible, but the structure will be functional nevertheless. An overrun in quantity is 
likely, because of less precise placement and increased stone displacement by the flow 
over the structure. This overrun will be offset in some cases by the relief provided by 
flow over the structure that would otherwise have been diverted around the end of the 
dike during construction, causing scour ahead of it, had it been above water during 
construction. 
10.4.3 SUBAQUEOUS PLACEMENT OF STONE OR SIMILAR MATERIALS 
Conventional draglines and bucket machines of all descriptions can be used 
successfully to place stone fill underwater. Bottom-dumping hopper barges can be used to 
increase rate of placement. This practice is more common in European practice than in the 
United States. Lacking such specialized equipment, ingenious use of available equipment, 
such as coal hoppers mounted between pontoon barges, can expedite the work. 
Subaqueous stone paving or granular filters can be placed more efficiently by 
specifying the quantity in terms of weight or volume per unit of area covered rather than in 
terms of blanket thickness. In-place thickness is difficult to measure underwater, and 
adequate coverage can be obtained by careful placement of the material using a grid system 
and pre-placement allocation of the amount of material to be placed per grid unit (for 
example, 7 tons per 100 square feet, in lieu of a paving thickness of 15 inches). Regardless 
of the placement and measurement procedure, the specified quantity should be greater than 
231 
2 1 
 | 
			||
![]()  | 
		||