| 
         | 
 
       | 
		||
        
![]() Monitoring and Maintenance of Stabilization Works 
11.2.3.6 Environmental Aspects 
The listing of this element last does not detract from its importance. It simply 
acknowledges that the project must perform its bank stabilization function adequately, else 
environmental function will likely be compromised as well. Also, some of the engineering 
elements just discussed, particularly geomorphology and hydraulics, have environmental 
implications as well. 
The environmental parameters which should be monitored can be defined by reviewing 
the environmental factors which were pertinent to the selection of the protection method. 
Environmental specialists should be involved in the monitoring as appropriate. 
11.2.4 FREQUENCY OF MONITORING 
The first few years after construction and the first major flood flow are the two critical 
periods in the life of bank protection works. Monitoring should be intensified during these 
periods. Although events such as toe scour and scour at termination points and bank heads 
may not fully develop during this period, major problem areas will usually become evident, 
and will help define the required monitoring intensity for the long-term. As a minimum, 
inspect the work immediately following the high flow season. If a need for immediate 
reconstruction or repairs is discovered, then the process of design and construction can be 
completed before the next high flow season. 
During these critical periods, an additional inspection during low water levels in late 
summer will allow an evaluation of the portion of the work that may have been underwater 
during earlier inspections, as well as an evaluation of vegetative growth during the summer. 
Problems with gradual deterioration of structural components does not carry the 
urgency of major changes in channel geometry or alignment, or major flaws in the initial 
design of the work. Therefore, any reasonable interval of monitoring will suffice for that 
element. 
Beyond these general guidelines, frequency of monitoring is determined either by 
regulation) or by engineering judgement, whichever results in the most frequent monitoring. 
Engineering judgement should take into account the safety factor of the original design and 
the consequences of failure (see 6.6), the severity of hydraulic conditions, and the degree of 
geomorphic instability of the stream. Monitoring of specific conditions such as channel 
velocity, waves, or ice forces should be timed to coincide with the occurrence of critical 
events if possible. 
240 
2 0 
 | 
			||
![]()  | 
		||