| 
         | 
 
       | 
		||
        
![]() Appendix A: Design Procedure for Riprap Armor 
(d) In some cases, a large part of the channel perimeter is covered with riprap; 
the average channel velocity, depth, and riprap size are dependent upon one 
another; and the solution becomes iterative. A trial riprap gradation is first 
assumed and resistance coefficients are computed using Equation (A.2). 
Then the four steps described in paragraph (b) are conducted. If the 
gradation found in Step 4 is equal to the assumed trial gradation, the 
solution is complete. If not a new trial gradation is assumed and the 
procedure is repeated. Example 2 demonstrates this procedure. 
2. 
Example 2 
a. Problem. Determine stable riprap size in a bend of a trapezoidal 
channel with essentially uniform flow. Bank slope is 1V on 2H and 
both the bed and banks will be protected with the same size of 
riprap. The bottom width is 140 ft, slope is 0.0017 ft/ft, and the 
design discharge is 13,500 cfs. Use 1D100(max) thickness and the 
same quarry as in Problem 1. Bend radius is 500 ft and bend angle 
is 120 deg. 
b. Solution. In this problem the solution is iterative; flow depth, 
velocity, and rock size depend on each other. Use Strictler's 
coefficient. Bend velocity is determined using Figure A.2. Assume 
trial gradation and solve for riprap size as shown in Tables A.2 and 
A.3. Use uniform flow computations to determine the following: 
Table A.2 Uniform Flow Computations 
Trial 
Normal 
Water- 
Average 
Side Slope 
D100(max) 
Manning's 
Depth 
Surface Width 
Velocity 
Depth 
(ft)1 
(fps)1 
(in.) 
n 
(ft) 
(ft) 
12 
0.034 
10.6 
182.4 
7.9 
8.5 
18 
0.036 
11.0 
184.0 
7.6 
8.8 
24 
0.038 
11.3 
185.2 
7.3 
9.0 
1 
From iterative solution of Manning's equation Q/A = (1.49/n)R2/3S1/2. 
Use velocity estimation and riprap size equations to obtain riprap 
size in Table A.3: 
A-25 
 | 
			||
![]()  | 
		||