| 
         | 
 
       | 
		||
        
![]() Appendix B: Bioengineering for Streambank Erosion Control -- Guidelines 
Bioengineering projects need to be observed early after project construction for signs of 
plant survival and development, as well as for streambank integrity. At least qualitative 
monitoring should be done to assure that detrimental phenomena do not jeopardize the 
project. For instance, Court Creek, Illinois, one of the project case studies discussed in 
Volume II, had an infestation of spider mites. Within a month or so after planting, spider 
mites had damaged almost all of the leaves on the willow that were being used for 
stabilization. Without remedial spraying, project failure could have resulted. In another case 
study, North River, Massachusetts (Volume II), a drought occurred the first year after 
planting and killed much of the planted emergent aquatic vegetation. Remedial planting had 
to be done the following year to compensate for drought mortality. Also, along with 
vegetative development, streambank integrity needs to be observed to ensure that unraveling 
of the bank is not occurring from such actions as undercutting of the toe or flanking at the 
upper or lower ends of the treated section. If this is occurring, then corrective measures need 
to be taken immediately, such as placing more rock or some other hard structure in those 
places. Projects should be monitored at least a couple of years after development at a 
minimum. Preferably, they should be monitored through 1-2 flood events where currents are 
directed on the treated bank. One can then assess whether the site remains stable or unravels. 
In the latter case, remediation can occur. Site monitoring in bioengineering projects should 
be written into the contract specifications so that early remediation does not become a part 
of operational and maintenance costs, which often have to be budgeted separately within 
many agencies. 
Direct Documentation of Erosion Protection 
Aerial Photographic Monitoring. Each bioengineering reach and associated treatment, 
e.g., rock toe with brush matting, vegetative geogrid, should be monitored for erosion directly 
by use of aerial photogrammetric techniques. This will allow evaluation of changes occuring 
at the land-water interface providing the procedures discussed below are used. 
Aerial photo coverage should be flown at least twice a year for the first 2-3 years or 
immediately after a flood event. Suggested times are in the spring and in the fall. Low-water 
periods are preferable. Photo flights should be highly controlled; that is, the scale of repeated 
flights must be the same. A suggested scale is 1:1,000. Also, three ground control points of 
known location and dimensions should be used per frame to provide accurate 
photogrammetric measurements and these should be orthogonally corrected when processed 
to negate distortion. Recommended film type in priority order is: (1) color infrared and (2) 
color. To allow comparisons of repeated photo coverage, flights must be made during low 
water periods and when river water levels correspond to each other; that is, at or below 
previous photographic periods. Overlays can be made on the photos which will delineate the 
water-interface boundary. Subsequent overlays can be compared showing any changes in the 
water-interface boundary (see Figure 44). Photographic measurements can then be made on 
the overlays to determine amount of surface area lost to erosion. 
B-79 
 | 
			||
![]()  | 
		||